Vacuum formed equipment covers are used across construction machinery because they can be produced without the tooling spend of injection moulding and without the weight of sheet metal. This page covers how 2 mm flame retardant ABS sheet is formed for construction machinery, what tolerances are realistic, and what has to be on the drawing before tooling starts.
The route below is the one used for most of the equipment covers shipped from this plant: sheet is heated on the forming machine, drawn over an aluminium or composite mould, cooled on a jig, then trimmed on a 5-axis router. For equipment covers the sheet gauge is selected from the load case rather than from habit, and flame retardant ABS is the material most often specified for this combination.

| Item | Value |
|---|---|
| Part type | equipment covers |
| Industry | construction machinery |
| Material | flame retardant ABS |
| Sheet thickness | 2 mm (1.5–12 mm available) |
| Maximum forming area | 3,000 × 2,000 mm |
| Typical tolerance | ±0.5 mm formed, ±0.2 mm on trimmed edges |
| Tooling | aluminium for production, composite for samples |
| First article | 7–15 working days |
| Production lead time | 3–4 weeks after approval |
| Finish | as formed, textured, painted or printed |
Flame retardant ABS is specified where the enclosure must meet UL94 V-0 or a comparable rail or appliance standard.

First article inspection covers critical dimensions, wall thickness, colour and texture against the approved sample. Batch releases carry a dimensional report, material certificate and, where agreed, PPAP or ISIR documentation.
Tooling is the main cost driver at low volume, so a 2 mm equipment covers for construction machinery is usually quoted with a composite or printed mould first and the aluminium tool cut once the design is frozen. That keeps the first article cost low and gives a real part to test before the production tool exists. The result is better appearance compared with the alternatives, and a piece price that stays stable across repeat releases.
Sample and first article tooling is usually cut in 7 to 15 working days. Production aluminium tools take 3 to 4 weeks depending on size and cooling layout.
A 3D file or drawing, the material if it is fixed, the annual quantity and the finish. Photos of the current part are enough for a first estimate.
Material certificates, dimensional reports and flame retardancy or food contact declarations are issued with the shipment where the specification requires them.
Send the drawing or a photo of the current equipment covers with the quantity and the finish. The first reply is a manufacturability review with the wall thickness, material and a quotation, so the decision is made on facts rather than on a price alone.