0 Views 2026-09-17 09:09 PPOEM

900 Wheel Covers ESD safe ABS Thermoformed for Atv And Utv in 4 Weeks

A ATV and UTV manufacturer came to us with wheel covers produced as an injection moulded part. The parts worked, but the cost and the lead time were holding up the programme. This is how they were reworked as vacuum formed wheel covers in 2 mm ESD safe ABS, and what the change delivered over the first 900 pieces.

wheel covers vacuum forming case for ATV and UTV

The starting point

  • Part: wheel covers for ATV and UTV
  • Existing route: an injection moulded part
  • Annual volume: 900 pieces
  • Problems: high unit cost, long lead time, and variation between batches

What was wrong with the old route

The previous injection moulded part needed several operations to reach finished shape, and every operation added both cost and a chance for variation. Weight was higher than it needed to be, and design changes meant new fixtures each time. For a programme of 900 pieces a year that is a poor fit.

What we built

ItemValue
Processthick gauge vacuum forming, 5-axis CNC trimming
MaterialESD safe ABS at 2 mm
Forming area usedup to 3,000 × 2,000 mm
Toolingaluminium production mould with a composite sample tool first
Finishas formed gloss
Batch size112 pieces per release
First article4 weeks from drawing release
Documentationdimensional report, material certificate, first article inspection

wheel covers formed from ESD safe ABS

Process route

  1. Parts are inspected, fitted with inserts or hardware if required, packed and shipped.
  2. Tooling is cut: aluminium for production volumes, composite or printed moulds for samples and first articles.
  3. Drawings are reviewed and a manufacturability report is issued with wall thickness, draft and radii marked up.
  4. The part cools on a jig so the shape is held while the material stabilises.
  5. Trimming is done on 5-axis routers or with a dedicated trim fixture to meet the drawing.
  6. The sheet is formed over the mould with vacuum and, where the draw is deep, with plug assist.

Results

  • cut lead time from 8 weeks to 3
  • First article approved in 4 weeks
  • Tooling amortised inside the first production batch
  • Repeat releases match the approved sample: tooling and programmes are stored against the part number
  • 900 pieces shipped to date with no dimensional escapes

Lessons from this project

  • The 2 mm was set from the load case, which avoided over specifying the sheet and paying for weight that was not needed
  • Draft and radii were checked before the tool was cut, so the first sample released without hand work
  • The trim line was placed on a flat face, which kept the router inside ±0.2 mm
  • Tooling and programmes are stored against the part number, so repeat releases need no new proving run

What the client said

“The sample arrived on the date we were given and it fitted the assembly on the first try. The wheel covers is lighter than the part it replaced and the finish holds up in the field. We now release the wheel covers against stored tooling and the paperwork comes with the shipment.”

Frequently asked questions

Could the same route work on a different part?

If the part is a shell, cover, tray or enclosure between 1.5 mm and 12 mm thick, it is almost always worth quoting. Send the drawing and the answer comes back with a material and a tooling plan.

How is the tooling handled between orders?

Tooling, trim fixtures and programmes are kept against the part number for the life of the programme, so a repeat release needs no new proving run.

finished wheel covers ready for shipment

Next step

Send the drawing or the existing wheel covers with the annual quantity. The reply is a manufacturability review, a material recommendation and a quotation within 24 hours.

Need a part like this?

Send the 3D file or drawing with your quantity — manufacturability review and quotation within 24 hours.

Get a Quote

Leave a Message