0 Views 2026-09-17 10:39 PPOEM

How a Aerospace Interiors Builder Replaced an injection moulded part with Vacuum Formed Display Shells in HDPE

When a aerospace interiors maker asked for a quotation on display shells, the parts were still being built as an injection moulded part. At 8000 pieces a year the tooling and the unit cost were both too high. The programme moved to a vacuum formed display shells in 10 mm HDPE, and the numbers changed with it.

display shells vacuum forming case for aerospace interiors

The starting point

  • Part: display shells for aerospace interiors
  • Existing route: an injection moulded part
  • Annual volume: 8000 pieces
  • Problems: high unit cost, long lead time, and variation between batches

What was wrong with the old route

The previous injection moulded part needed several operations to reach finished shape, and every operation added both cost and a chance for variation. Weight was higher than it needed to be, and design changes meant new fixtures each time. For a programme of 8000 pieces a year that is a poor fit.

What we built

ItemValue
Processthick gauge vacuum forming, 5-axis CNC trimming
MaterialHDPE at 10 mm
Forming area usedup to 3,000 × 2,000 mm
Toolingaluminium production mould with a composite sample tool first
Finishas formed gloss
Batch size1000 pieces per release
First article4 weeks from drawing release
Documentationdimensional report, material certificate, first article inspection

display shells formed from HDPE

Process route

  1. The sheet is formed over the mould with vacuum and, where the draw is deep, with plug assist.
  2. Sheet is dried when the material needs it, then heated to forming temperature on the machine.
  3. Trimming is done on 5-axis routers or with a dedicated trim fixture to meet the drawing.
  4. Tooling is cut: aluminium for production volumes, composite or printed moulds for samples and first articles.
  5. Parts are inspected, fitted with inserts or hardware if required, packed and shipped.
  6. The part cools on a jig so the shape is held while the material stabilises.

Results

  • cut lead time from 8 weeks to 3
  • First article approved in 4 weeks
  • Tooling amortised inside the first production batch
  • Repeat releases match the approved sample: tooling and programmes are stored against the part number
  • 8000 pieces shipped to date with no dimensional escapes

Lessons from this project

  • The 10 mm was set from the load case, which avoided over specifying the sheet and paying for weight that was not needed
  • Draft and radii were checked before the tool was cut, so the first sample released without hand work
  • The trim line was placed on a flat face, which kept the router inside ±0.2 mm
  • Tooling and programmes are stored against the part number, so repeat releases need no new proving run

What the client said

“The sample arrived on the date we were given and it fitted the assembly on the first try. The display shells is lighter than the part it replaced and the finish holds up in the field. We now release the display shells against stored tooling and the paperwork comes with the shipment.”

Frequently asked questions

Could the same route work on a different part?

If the part is a shell, cover, tray or enclosure between 1.5 mm and 12 mm thick, it is almost always worth quoting. Send the drawing and the answer comes back with a material and a tooling plan.

How is the tooling handled between orders?

Tooling, trim fixtures and programmes are kept against the part number for the life of the programme, so a repeat release needs no new proving run.

finished display shells ready for shipment

Next step

Send the drawing or the existing display shells with the annual quantity. The reply is a manufacturability review, a material recommendation and a quotation within 24 hours.

Need a part like this?

Send the 3D file or drawing with your quantity — manufacturability review and quotation within 24 hours.

Get a Quote

Leave a Message