When a beauty and spa equipment maker asked for a quotation on machine housings, the parts were still being built as a welded steel fabrication. At 900 pieces a year the tooling and the unit cost were both too high. The programme moved to a vacuum formed machine housings in 6 mm polycarbonate, and the numbers changed with it.

The previous welded steel fabrication needed several operations to reach finished shape, and every operation added both cost and a chance for variation. Weight was higher than it needed to be, and design changes meant new fixtures each time. For a programme of 900 pieces a year that is a poor fit.
| Item | Value |
|---|---|
| Process | thick gauge vacuum forming, 5-axis CNC trimming |
| Material | polycarbonate at 6 mm |
| Forming area used | up to 3,000 × 2,000 mm |
| Tooling | aluminium production mould with a composite sample tool first |
| Finish | silk screened markings |
| Batch size | 112 pieces per release |
| First article | 4 weeks from drawing release |
| Documentation | dimensional report, material certificate, first article inspection |

“The sample arrived on the date we were given and it fitted the assembly on the first try. The machine housings is lighter than the part it replaced and the finish holds up in the field. We now release the machine housings against stored tooling and the paperwork comes with the shipment.”
If the part is a shell, cover, tray or enclosure between 1.5 mm and 12 mm thick, it is almost always worth quoting. Send the drawing and the answer comes back with a material and a tooling plan.
Tooling, trim fixtures and programmes are kept against the part number for the life of the programme, so a repeat release needs no new proving run.

Send the drawing or the existing machine housings with the annual quantity. The reply is a manufacturability review, a material recommendation and a quotation within 24 hours.
Send the 3D file or drawing with your quantity — manufacturability review and quotation within 24 hours.
Leave a Message