6 mm food grade polypropylene centre consoles manufactured for truck and bus: food grade polypropylene sheet vacuum formed to drawing, 5-axis trimmed, MOQ 1 pieces, first article in 7-15 working days.

Free Quote

These food grade polypropylene centre consoles are thick gauge vacuum formed parts supplied to drawing for truck and bus. They are formed from food grade polypropylene sheet at 6 mm, trimmed on 5-axis routers and inspected against the drawing before packing. Buyers choose this route where a metal fabrication is too heavy, or where injection moulding tooling cannot be justified for the volume.

centre consoles

Product specification

ItemValue
Productcentre consoles
Typical applicationtruck and bus
Materialfood grade polypropylene
Standard gauge6 mm
Gauge range available1.5–12 mm
Maximum formed size3,000 × 2,000 mm
Formed tolerance±0.5 mm typical
Trim tolerance±0.2 mm on router cut edges
Draft angle3 degrees minimum, 5 degrees preferred
Finish optionsclear protective film, soft touch coating, mould texture
Minimum order1 pieces
Lead time to first article7–15 working days
Toolingaluminium production tool, composite or printed sample tool
OriginChina, export packed

Key features

  • One piece shell replaces a fabrication, so assembly hours drop
  • food grade polypropylene keeps the weight down while stiffness is held through the formed shape
  • Clear protective film finish as standard, further finishes on request
  • Trimmed on 5-axis routers, so mounting holes and cut outs match the drawing
  • Tooling stored against the part number for repeat and spare orders
  • REACH compliant sheet available

Typical applications

  • engine tunnel covers
  • stepwell panels
  • interior trim panels
  • bunk liners
  • centre consoles used across general truck and bus builds

How it is made

  1. Parts are inspected, fitted with inserts or hardware if required, packed and shipped.
  2. Trimming is done on 5-axis routers or with a dedicated trim fixture to meet the drawing.
  3. The sheet is formed over the mould with vacuum and, where the draw is deep, with plug assist.
  4. Sheet is dried when the material needs it, then heated to forming temperature on the machine.
  5. The part cools on a jig so the shape is held while the material stabilises.

forming centre consoles from food grade polypropylene sheet

Material: food grade polypropylene

Food grade polypropylene is used for trays, hoppers and liners that touch product, and it can be washed with caustic cleaners.

Design notes

  • hold the draw ratio near 1:1 for deep parts, or specify plug assist
  • keep a draft angle of at least 3 degrees on vertical walls so the part releases cleanly
  • use corner radii of at least three times the sheet thickness to avoid thinning
  • call out the finish on the drawing: mould texture, paint, or as-formed gloss

Finishing and assembly options

  • clear protective film
  • soft touch coating
  • mould texture
  • Threaded inserts, PEM fasteners and brackets fitted before dispatch
  • Mating parts can be trial assembled before the first article ships

Quality

Batch releases carry a dimensional report, material certificate and, where agreed, PPAP or ISIR documentation. Moulds, trim fixtures and programmes are stored against the part number, so a repeat order matches the first batch.

  • ISO 9001 quality system
  • REACH compliant sheet available
  • UL94 V-0 grades available

Packing and delivery

Each part is bagged, edges protected with foam, then cartonised for container loading. Standard lead time to first article is 7–15 working days, and repeat releases ship against stored tooling without a new proving run.

packed centre consoles ready for shipment

Frequently asked questions

Can you make it in another material?

Any grade in this family can be swapped in. Send the requirement and the material will be quoted with the price difference shown.

How fast is the first article?

Seven to fifteen working days from drawing release for sample tooling, with production tooling in three to four weeks.

Are spare parts available later?

Tooling is stored against the part number for the life of the programme, so replacements or spare panels can be released at any time.

Request a quotation

Send the drawing or a photo of the current centre consoles with the quantity and the finish required. The reply covers material choice, wall thickness, tooling route and price, so the decision is made on a complete picture.