10 mm TPO splash guards manufactured for defence and security equipment: TPO sheet vacuum formed to drawing, 5-axis trimmed, MOQ 1 pieces, first article in 7-15 working days.
Free QuoteThese TPO splash guards are thick gauge vacuum formed parts supplied to drawing for defence and security equipment. They are formed from TPO sheet at 10 mm, trimmed on 5-axis routers and inspected against the drawing before packing. Buyers choose this route where a metal fabrication is too heavy, or where injection moulding tooling cannot be justified for the volume.

| Item | Value |
|---|---|
| Product | splash guards |
| Typical application | defence and security equipment |
| Material | TPO |
| Standard gauge | 10 mm |
| Gauge range available | 1.5–12 mm |
| Maximum formed size | 3,000 × 2,000 mm |
| Formed tolerance | ±0.5 mm typical |
| Trim tolerance | ±0.2 mm on router cut edges |
| Draft angle | 3 degrees minimum, 5 degrees preferred |
| Finish options | two coat polyurethane paint, powder coat finish, UV stabilised as formed |
| Minimum order | 1 pieces |
| Lead time to first article | 7–15 working days |
| Tooling | aluminium production tool, composite or printed sample tool |
| Origin | China, export packed |

TPO sheet is used where the part lives outdoors: it stays flexible in the cold and resists UV without a coating.
First article inspection covers critical dimensions, wall thickness, colour and texture against the approved sample. Sheet thickness is checked on the formed part at the points shown on the drawing, and the readings go into the report.
Large panels are crated in made to measure wooden cases with corner protection. Standard lead time to first article is 7–15 working days, and repeat releases ship against stored tooling without a new proving run.

Seven to fifteen working days from drawing release for sample tooling, with production tooling in three to four weeks.
Any grade in this family can be swapped in. Send the requirement and the material will be quoted with the price difference shown.