3 mm polypropylene skid plates manufactured for telecom and network cabinets: polypropylene sheet vacuum formed to drawing, 5-axis trimmed, MOQ 50 pieces, first article in 3-4 weeks.
Free QuoteThese polypropylene skid plates are thick gauge vacuum formed parts supplied to drawing for telecom and network cabinets. They are formed from polypropylene sheet at 3 mm, trimmed on 5-axis routers and inspected against the drawing before packing. Buyers choose this route where a metal fabrication is too heavy, or where injection moulding tooling cannot be justified for the volume.

| Item | Value |
|---|---|
| Product | skid plates |
| Typical application | telecom and network cabinets |
| Material | polypropylene |
| Standard gauge | 3 mm |
| Gauge range available | 1.5–12 mm |
| Maximum formed size | 3,000 × 2,000 mm |
| Formed tolerance | ±0.5 mm typical |
| Trim tolerance | ±0.2 mm on router cut edges |
| Draft angle | 3 degrees minimum, 5 degrees preferred |
| Finish options | powder coat finish, soft touch coating, satin finish |
| Minimum order | 50 pieces |
| Lead time to first article | 3–4 weeks |
| Tooling | aluminium production tool, composite or printed sample tool |
| Origin | China, export packed |

Polypropylene survives repeated impact and most cleaning chemicals. Its low forming temperature keeps cycles short, but it shrinks more, so the mould is cut with the shrink factor built in.
Batch releases carry a dimensional report, material certificate and, where agreed, PPAP or ISIR documentation. Sheet thickness is checked on the formed part at the points shown on the drawing, and the readings go into the report.
Large panels are crated in made to measure wooden cases with corner protection. Standard lead time to first article is 3–4 weeks, and repeat releases ship against stored tooling without a new proving run.

Any grade in this family can be swapped in. Send the requirement and the material will be quoted with the price difference shown.
Seven to fifteen working days from drawing release for sample tooling, with production tooling in three to four weeks.
Tooling is stored against the part number for the life of the programme, so replacements or spare panels can be released at any time.
Send the drawing or a photo of the current skid plates with the quantity and the finish required. The reply covers material choice, wall thickness, tooling route and price, so the decision is made on a complete picture.
Leave a Message