0 Views 2026-09-17 09:11 PPOEM

Specify fixture design – Method and Checks – Short Runs

This guide covers how to specify fixture design on a vacuum formed part: what the designer has to decide, what the mould maker needs to know, and the checks that catch problems before tooling is cut.

Specify fixture design – Method and Checks – Short Runs

What it affects

The main effects are on wall thickness, cycle time and how much hand work the part needs after forming. On a thick gauge part these three decide the piece price, so the decision taken here shows up in every release afterwards.

Typical values

ItemValue
Sheet range1.5–12 mm for thick gauge work
Forming areaup to 3,000 × 2,000 mm
Formed tolerance±0.5 mm typical
Trimmed tolerance±0.2 mm on router cut edges
Draft angle3 degrees minimum, 5 degrees preferred
Corner radiusat least 3 × sheet thickness
Cycle time60–180 s depending on gauge and material

How it is controlled

  1. Trimming is done on 5-axis routers or with a dedicated trim fixture to meet the drawing.
  2. Drawings are reviewed and a manufacturability report is issued with wall thickness, draft and radii marked up.
  3. The sheet is formed over the mould with vacuum and, where the draw is deep, with plug assist.
  4. The part cools on a jig so the shape is held while the material stabilises.
  5. Parts are inspected, fitted with inserts or hardware if required, packed and shipped.

thermoforming production control

Common mistakes

  • keep a draft angle of at least 3 degrees on vertical walls so the part releases cleanly
  • call out the finish on the drawing: mould texture, paint, or as-formed gloss
  • hold the draw ratio near 1:1 for deep parts, or specify plug assist
  • avoid sharp steps in the mould, which show as chill marks on the finished surface

How to specify it on the drawing

Put the decision on the drawing rather than in an email: state the material and grade, the gauge, the finish, the surfaces that must not carry marks, and the tolerance that applies to the trimmed edges. Where the part has to mate with another component, mark the datum faces so the trim fixture and the inspection report use the same reference. A drawing that states these points removes most of the questions that otherwise surface during sampling.

Checklist before tooling is cut

  • Material and grade fixed, including flame retardancy, UV or food contact requirements
  • Gauge selected from the load case, not from habit
  • Draft angle and corner radii checked against the sheet thickness
  • Trim line placed on a face the router can reach
  • Finish and colour standard agreed, with a reference if the colour is critical
  • Inspection points agreed and noted for the dimensional report

Related terms

  • Hot wire cutting
  • Cnc trimming
  • Snap fit design
  • Gloss measurement
  • Cost per part
  • Prototype tooling

Frequently asked questions

Does this change the tooling cost?

Yes. Decisions taken at drawing stage move the tooling cost more than any later change, which is why the manufacturability review is done before the tool is cut.

What information do you need to advise on it?

A 3D file, the material if it is fixed, the annual quantity and the finish. With those the answer comes back with a recommended route and a quotation.